Battery boom alerts 50 Hertz to grid connection shortage for new industrial plants
Grid operator 50 Hertz is warning about a years-long blockade of grid connections for new industrial businesses caused by the boom in large-scale battery storage. Head of Management Stefan Kapferer told the "Redaktionsnetzwerk Deutschland" (Saturday editions) that the storage companies proceeded very professionally when applying for grid connections.
Industrial businesses were often left behind because they did not yet know part of their future demand. Kapferer stated that there is increasing danger that storage projects will not be realized, but grid connections will still be reserved and built in substations for them. The possible consequence would be that connections for new industrial settlements, especially in Eastern Germany, will be missing for years.
According to Kapferer, 50 Hertz alone currently has around 160 applications for battery storage projects with a high level of maturity. Nationwide, grid operators have already pledged connection capacities exceeding 100 gigawatts-for comparison: the maximum demand in the entire German electricity grid is about 80 gigawatts.
The head of 50 Hertz demands a change to the legal rules to enable industrial companies to be prioritized when receiving grid connections. Kapferer argued that the emergency brake must be pulled. The Federal Government must implement this quickly in the planned network package.
Large-scale battery storage is considered a central component of the energy transition. They balance the fluctuating supply from wind and solar energy by absorbing electricity from wind and solar plants when production is abundant and injecting it into the grid when electricity prices are high due to scarcity.