Stress test suggests nuclear power reserves until April to prevent potential blackouts
On Monday, the four German transmission system operators 50Hertz, Amprion, TenneT, and TransnetBW presented the results of the second grid stress test. Commissioned by the Federal Ministry for Economic Affairs, they examined the security of the electricity grid for this winter under tightened external conditions.
The result: "crisis-like situations in the power system" lasting several hours are "very unlikely for the upcoming winter, but currently cannot be completely ruled out", as stated during the presentation on Monday evening. Regarding emergency safeguards, the Ministry stated that the two southern nuclear power plants, Isar 2 and Neckarwestheim, are to be kept as a "temporally and substantively limited nuclear power plant strategic reserve" until mid-April 2023, "in order to be able to provide an additional contribution to the power grid in southern Germany for 2022/23 over the winter if necessary". According to the Ministry, all three nuclear power plants currently still connected to the grid in Germany are scheduled to go offline at the end of 2022, and no new fuel elements will be loaded. Federal Minister for Economic Affairs Robert Habeck (The Greens) stated on Monday that the reserve will also end in mid-April 2023.
The new calculation assumed, among other things, that a large portion of French nuclear power plants would not return to the market by winter, that low water levels in rivers would further restrict hard coal deliveries, that half of the gas-fired power plants in southern Germany would be unavailable, and that demand from space heaters would increase consumption peaks by several gigawatts. Furthermore, the grid operators based their calculations on a gas price of 300 euros per megawatt-hour. "Specifically, the results of the calculations show that in some scenarios, demand in certain regions of the European electricity market cannot be fully met without additional measures", the Ministry summarized the stress test. In the extreme scenario, such situations "also occur in Germany for very short periods, meaning a few hours per year".